Establishment year: Initially established in 1984 and the present infrastructure was built in 1988 Area coverage : 9.37 acres Thram no. 425 under Kikhorthang Gewog and Thram no. 498 under Goseling Gewog Total strength : 110 Nangtens Second Floor (Top Floor): Goenkhang and Guru Dorji Drolo First Floor : Neten Chudrug Lhakhang with Tempa Ground Floor : Tempa, Guru Rimpochey and Zhabdrung Ngawang Namgyel
|
REPORT ON THE CONSTRUCTION OF NEW TSIRANG DZONG. |
|
1. Location: Damphu 2. Size of the dzong: A) Length=64.00m B) Breadth=57.00m C) Total plinth area=3650.18sq.m
3. Start of the project: January 2004.
4. Completion time: March 2008.
5. Type of the structure: Load bearing stone masonry wall in cement mortar/RCC.
6. Total project cost: Nu 113.382 million (may increase to Nu 130.00 million Approx.) 7. Type of structure: Load bearing stone masonry wall in cement mortar/RCC
8. Total project cost: Nu.113.382 million (may increase to Nu. 130.00 million Approx) 9. Total expenditure: Nu. 70.5588 million
10. Regular staff : - Site Engineer -1 - J.E (Electrical) -1 - Timber in-charge -1 - Driver (Tripper) -1
11. Supporting staff: - Store Asset. -1 - Timber Asset. -1 - Lajab -3 - Zopen gongwog -2 - Dozow lopen -1
12. Total Labour strength: 150 t0 175nos.
13. Situation: Actually the due date for completing the new dzong is on the march 2008 but due to the following reasons it may not be completed on the projected time. The reasons are: -Lack of timber supply. -Lack of regular and consistent power supply.
|